The fallout from grassroots opposition to data centers is expanding into the ABS market.
A green energy group is denouncing an upcoming utility-fee securitization in Virginia from Dominion Energy for harming consumers – and it says data centers are a major factor in the utility company’s need to tap the ABS market.
Dominion on 21 September got approval from state regulators to issue a $922m securitization, Virginia Power Fuel Securitization II, backed by payments charged to customers to recoup the cost of fuel generation from July 2025-June 2026. Dominion says the shortfall is due to unusually cold weather last winter, which increased demand for and the price of natural gas.
But the Institute for Energy Economics and Financial Analysis, a vocal critic of data centers, isn’t so sure.
“Dominion Energy has not been bad at forecasting demand,” said Dennis Wamsted, energy analyst at IEEFA, in an email to 9fin. “What they have been bad at is forecasting the cost of that energy, which can swing wildly based on weather. The key linking those two points is that the vast majority of the increase in Dominion's sales since the pandemic is due to rising demand from data centers.”